Performance Diagnostic — Stage 1

Descriptive · Audit-safe · Derived from 96 validated plant records · 100% data coverage
ClientSample India Power Co
Plant / UnitPlant-1 · U1
Analysis Period01 Jan – 04 Jan 2026
ReportYBG-ST1-20260430-4D44
Issued30 Apr 2026
DAILY RECOVERABLE VALUE
INR 3,10,198 per day
USD $3,728 / day · From the unit's own demonstrated best performance. Not theoretical.
ANNUALISED VALUE
INR 11.3 crore / year
USD $1.36M / year · INR 12,925 / hour
PERFORMANCE GAP
+3.3%
above best-achieved
RECOVERABLE FUEL
2.59 t/h
above best
CURRENT PERFORMANCE
operator-native units
BEST-ACHIEVED
demonstrated in dataset

This cover is a commercial summary only. The attached technical report is descriptive and audit-safe: findings are derived deterministically from validated plant data using YBG's Observe → Quantify → Verify framework. No operational recommendations, set-points, or improvement forecasts are provided. USD reference: 1 USD = 83.2 INR.

Activate Stage 1 ongoing verification · admin@ybgglobal.com
Stage 1 — Performance Diagnostic · Page 1 of 17 · ybgglobal.com
YBG Global

YBG ControlAlign™

Aligning Operation to Your Plant's Best Demonstrated Performance

Diagnostic Report — Stage 1

Performance Diagnostic
Date of Issue30 Apr 2026 11:07
Analysis Period01 Jan 2026 00:00 – 04 Jan 2026 23:00
Source DataValidated client operating dataset
ScopeSingle-unit performance behaviour
External BenchmarksNone
ClientSAMPLE INDIA POWER CO
PlantPlant-1
UnitU1
Report NumberYBG-ST1-20260430-4D44

1. Purpose of Report

This report describes the observed performance behaviour of the unit using the supplied operating data. It is descriptive and audit-safe: results are derived deterministically from validated rows in the dataset, and no operational recommendations, set-points, or improvement forecasts are provided. External benchmarks are not used.

Stage 1 — Performance Diagnostic · Page 2 of 17 · ybgglobal.com

Table of Contents

  1. 1. Purpose of Report
  2. 2. Executive Summary
  3. 3. Data Validity & Stability
  4. 4. Best-Achieved Performance Range
  5. 4A. Best-Performance Operating Conditions
  6. 4B. Operating Profile — Load vs Thermal State
  7. 5. Deviation Analysis
  8. 5A. Load-Band Performance Comparison
  9. 6. Performance vs Load — Best-Achieved vs Current
  10. 6A. Performance Index vs Load — Best-Achieved vs Current
  11. 7. Economic Impact
  12. 8. Diagnostic Insight — Operating Profile
  13. 9. Load Context
  14. 10. Reference Operating Windows
  15. 11. Traceability & Data Integrity
  16. 12. Definitions
  17. 13. Closing Statement
  18. 14. Operational Continuation (Optional)
Stage 1 — Performance Diagnostic · Page 3 of 17 · ybgglobal.com

2. Executive Summary

DAILY RECOVERABLE VALUE
INR 310,198 per day
USD $3,728 per day
ANNUALISED RECOVERABLE VALUE
INR 11.3 crore / year
USD $1.36M / year · INR 12,925 / hour

The unit's own validated operating data demonstrates a recoverable performance gap between current operation and the unit's best-achieved performance across comparable load conditions. The value is quantified deterministically; it is not modelled, benchmarked, or forecast.

Stage 1 — Performance Diagnostic · Page 4 of 17 · ybgglobal.com

3. Data Validity & Stability

Total records ingested96
Records validated96
Coverage100%
Exclusions0
Period span96 hours

Exclusions by reason

None — all parsed rows passed0
Stage 1 — Performance Diagnostic · Page 5 of 17 · ybgglobal.com

4. Best-Achieved Performance Range

VariableRange LowRange HighObserved MeanUnits
Load215.0260.0237.5MW
Steam temperature285.0292.0287.7°C
Steam flow700.00765.00732.50t/h

Range derived from the unit's own demonstrated best performance across validated load conditions.

Stage 1 — Performance Diagnostic · Page 6 of 17 · ybgglobal.com

4A. Best-Performance Operating Conditions

SignalBest-Achieved RangeCurrent MeanInterpretationUnits
Combustion indicator A3.00 – 3.403.82Outside best
Thermal-state indicator974 – 978974Within range°C
Steam temperature285 – 292287.9Within range°C
Stage 1 — Performance Diagnostic · Page 7 of 17 · ybgglobal.com

4B. Operating Profile — Load vs Thermal State

Chart — Operating Profile
[chart visualisation — sanitized public sample]
X: Load (MW)Y: Thermal-state indicator
  • Grey = all validated observations
  • Green = best-achieved performance band
  • Orange = current operation
Stage 1 — Performance Diagnostic · Page 8 of 17 · ybgglobal.com

5. Deviation Analysis

SignalBest-AchievedCurrent MeanGapHours OutsideStatus
PerformanceBestCurrent+3.3%11.9 h (12.5%)OUT
Thermal-state indicator976974−1.817.8 h (18.8%)WATCH
Steam temperature287.7287.9+0.217.8 h (18.8%)WATCH
Combustion indicator3.00 – 3.403.82+0.42OK
Stage 1 — Performance Diagnostic · Page 9 of 17 · ybgglobal.com

5A. Load-Band Performance Comparison

Performance is compared per load band between current operation and the unit's own best-achieved performance, derived deterministically from validated plant data. Bands with insufficient validated records are not shown.

Load bandRecordsCurrentBest-achievedGap (%)
Low band32Index 1.033Index 1.000+3.3
Mid band41Index 1.034Index 1.000+3.4
High band23Index 1.041Index 1.000+4.1

Current = per-band mean. Best-Achieved = the unit's own demonstrated best per load band, derived deterministically from validated plant data.

Stage 1 — Performance Diagnostic · Page 10 of 17 · ybgglobal.com

6. Performance vs Load — Best-Achieved vs Current

Chart — Performance vs Load
[chart visualisation — sanitized public sample]
X: Load (MW)Y: Performance (operator-native units)
  • Grey = validated observations
  • Green = best-achieved per load band
  • Orange = current operation (per-band mean)
  • Shaded = performance gap

Performance gap quantified. Financial impact: INR 3,10,198/day (USD $3,728/day).

Stage 1 — Performance Diagnostic · Page 11 of 17 · ybgglobal.com

6A. Performance Index vs Load — Best-Achieved vs Current

Chart — Performance Index
[chart visualisation — sanitized public sample]
X: Load (MW)Y: Performance Index
  • Grey = validated observations
  • Green = best-achieved per load band
  • Orange = current operation
  • Shaded = performance gap

Performance gap: +3.3% above the unit's best-achieved performance. Financial impact: INR 3,10,198/day (USD $3,728/day).

Stage 1 — Performance Diagnostic · Page 12 of 17 · ybgglobal.com

7. Economic Impact

TermValueUnits / Basis
Daily recoverable value3,10,198INR / day
Daily recoverable value3,728USD / day
Annualised11.3 croreINR / year
Annualised1.36 millionUSD / year
Hourly12,925INR / hour

This value represents the cost associated with the observed performance deviation under current operating conditions. The economic impact is derived deterministically from the same load-normalised performance gap shown above.

Stage 1 — Performance Diagnostic · Page 13 of 17 · ybgglobal.com

8. Diagnostic Insight — Operating Profile

The unit operates within its safe and stable thermal envelope. The observed performance gap reflects opportunities to consistently hold the operating profile closer to the unit's own best-achieved performance, without changes to equipment, control systems, or operating philosophy.

9. Load Context

Mean load over the analysis period: 237.5 MW. Load distribution: balanced across three bands (low / mid / high). All findings are normalised by load.

10. Reference Operating Windows

Reference windows are derived per load band from the unit's own demonstrated best performance. They are descriptive, not prescriptive.

Stage 1 — Performance Diagnostic · Page 14 of 17 · ybgglobal.com

11. Traceability & Data Integrity

SourceValidated client operating dataset (96 records, 100% coverage)
Report numberYBG-ST1-20260430-4D44
Analysis period01 Jan 2026 00:00 – 04 Jan 2026 23:00
Plant countryIN
External benchmarksNone

Performance derived deterministically from validated plant data. Signals not present in dataset are excluded from analysis.

Stage 1 — Performance Diagnostic · Page 15 of 17 · ybgglobal.com

12. Definitions

Best-Achieved Performance
The unit's own demonstrated best performance across comparable load conditions, derived deterministically from validated plant data. Not a model, not a benchmark, not a forecast.
Combustion Condition Indicator
A measured operating parameter used to characterise the unit's combustion behaviour within the validated dataset.
Performance Gap
The quantified difference between current operation and the unit's own best-achieved performance, expressed in operator-native units.

13. Closing Statement

This report is descriptive and audit-safe. All values are bounded by the 96 validated records in the analysis period. No operational recommendations, set-points, or improvement forecasts are provided.

Stage 1 — Performance Diagnostic · Page 16 of 17 · ybgglobal.com

14. Operational Continuation (Optional)

This report identifies a recoverable value of INR 3,10,198/day (USD $3,728/day) under current operation. Realising and sustaining this value requires continuous verification against the identified best-achieved performance.

Stage 1 ongoing verification provides continuous data ingestion, automated best-achieved tracking, and daily savings verification.

Activate Stage 1 ongoing verification · admin@ybgglobal.com · ybgglobal.com
Stage 1 — Performance Diagnostic · Page 17 of 17 · ybgglobal.com
End of sample · 17 pages
© YBG Group International · Sample report is illustrative and sanitized for public viewing. Reproduction, redistribution, or capture is prohibited.